What does joint photographing mean in gypsum board finishing?
Correct Answer
A) Visible telegraphing of joints or fastener patterns through the final finish
Joint photographing is the visible telegraphing of joints, fasteners, or surface differences through the final finish. Other choices confuse the term with documentation, fire testing, or layout.
Why This Is the Correct Answer
Joint photographing is the visible telegraphing of joints, fasteners, or surface differences through the final finish. Other choices confuse the term with documentation, fire testing, or layout.
Why the Other Options Are Wrong
Option B: Classify the condition as a required photo log for inspections
Choice B gives A required photo log for inspections. Its specific error: it answers the Gypsum joint photographing prompt with the wrong practical move.
Option C: Classify the condition as a method for measuring wall fire resistance
Choice C (A method for measuring wall fire resistance) is rejected because it leaves out the controlling Gypsum joint photographing result: Visible telegraphing of joints or fastener patterns through the final finish.
Option D: Classify the condition as a way to locate ceiling hangers
In finishes, A way to locate ceiling hangers is the wrong selection for Gypsum joint photographing: the choice would not get the project to Visible telegraphing of joints or fastener patterns through the final finish, which is the Gypsum joint photographing result verified by the source.
Memory Technique
Use gypsum joint photographing as the label and Visible telegraphing of joints or fastener patterns through the final finish as the definition to recall under pressure.
Reference Hint
Open Gypsum Construction Handbook, 7th Ed., 2014; use the index entry or section for "Gypsum board finishing terminology" to confirm that Joint photographing is the visible telegraphing of joints, fasteners, or surface differences through the final finish.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A pump schedule lists a motor in horsepower, but the electrical coordination table uses watts. Which conversion should be recognized for one horsepower?
Next Question
A ready-mix load waits through a site access delay and arrives near the specification's maximum discharge time. Slump is low and the batch ticket shows no approved retarder. What should happen before placement?