A storefront opening is 48 ft wide and 10 ft high. Deduct two aluminum entrance doors, each 3 ft by 7 ft, from the glazed area. What net glass area remains?
Correct Answer
A) 438 sf
Gross opening area is 48 x 10 = 480 sf. The two doors deduct 2 x 3 x 7 = 42 sf, leaving 480 - 42 = 438 sf. Other choices deduct one door, ignore the doors, or add door area.
Why This Is the Correct Answer
Gross opening area is 48 x 10 = 480 sf. The two doors deduct 2 x 3 x 7 = 42 sf, leaving 480 - 42 = 438 sf. Other choices deduct one door, ignore the doors, or add door area.
Why the Other Options Are Wrong
Option B: 456 sf
storefront glass area, choice b: 456 sf adds an extra unstated add-on/subtraction; the numeric gap is 18.
Option C: 480 sf
storefront glass area, choice c: 480 sf is an intermediate from the steps (Gross opening area is 48 x 10 = 480 sf.); the calculation continues to 438 sf.
Option D: 522 sf
storefront glass area, choice d: 522 sf adds an extra unstated add-on/subtraction; the numeric gap is 84.
Memory Technique
Keep a ledger line beside storefront glass area: if one number is skipped, the option drifts away from 438 sf.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Storefront glazing area takeoff" to confirm that Gross opening area is 48 x 10 = 480 sf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A civil foreman reviews the trench plan: what document normally commits a supplier to furnish materials at agreed price, terms, and delivery requirements?
Next Question
A crew begins laying pipe in a 6 ft deep trench, and the only ladder is 45 ft from the work face. What is the appropriate correction?