A crew begins laying pipe in a 6 ft deep trench, and the only ladder is 45 ft from the work face. What is the appropriate correction?
Correct Answer
C) Place safe egress so workers have no more than 25 ft of lateral travel
For trenches 4 ft or deeper, OSHA requires safe egress so employees travel no more than 25 ft laterally. Other choices leave access too far away or substitute unsafe climbing routes.
Why This Is the Correct Answer
For trenches 4 ft or deeper, OSHA requires safe egress so employees travel no more than 25 ft laterally. Other choices leave access too far away or substitute unsafe climbing routes.
Why the Other Options Are Wrong
Option A: Leave the ladder because the trench is straight
Choice A gives Leave the ladder because the trench is straight. Its specific error: the option does not produce the required Missing trench access outcome, Place safe egress so workers have no more than 25 ft of lateral travel.
Option B: Let workers climb the trench shield spreaders
Choice B (Let workers climb the trench shield spreaders) is rejected because it points to Let workers climb the trench shield spreaders, but.
Option D: Require workers to exit only at lunch and at shift end, using the trench wall for access
The trap in D is Require workers to exit only at lunch and end of shift. That selection is wrong because the option delays or omits the controlling step.
Memory Technique
Picture a weep path on the jobsite; missing trench access is solved by the action that leads to Place safe egress so workers have no more than 25 ft of lateral travel.
Reference Hint
Open 29 CFR Part 1926, Subpart P - Excavations; use 29 CFR 1926.651(c)(2) to confirm that For trenches 4 ft or deeper, OSHA requires safe egress so employees travel no more than 25 ft laterally.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?