A civil foreman reviews the trench plan: what document normally commits a supplier to furnish materials at agreed price, terms, and delivery requirements?
Correct Answer
B) Purchase order
Purchase order is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 282.
Why This Is the Correct Answer
Purchase order is the controlling requirement
Why the Other Options Are Wrong
Option A: RFI log
Choice A gives RFI log. Its specific error: the option does not produce the required Purchase order outcome, Purchase order.
Option C: Use the payment application file as the backup record for purchase order
In procurement and contracting, Punch list is the wrong selection for Purchase order: it answers the Purchase order prompt with the wrong practical move.
Option D: Noncollusion affidavit
The trap in D is Noncollusion affidavit. That selection is wrong because it leaves out the controlling Purchase order result: Purchase order.
Memory Technique
File purchase order under a index tab: condition first, number or duty second, answer Purchase order.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Purchase orders" to confirm that Purchase order is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Vertical reinforcing is required at 32 in. on center along an 80 ft CMU wall, with a bar at each end. Each bar length including splice projection is 15 ft. What total reinforcing length is needed?
Next Question
A storefront opening is 48 ft wide and 10 ft high. Deduct two aluminum entrance doors, each 3 ft by 7 ft, from the glazed area. What net glass area remains?
