A civil foreman reviews the trench plan: what document normally commits a supplier to furnish materials at agreed price, terms, and delivery requirements?
Correct Answer
B) Purchase order
Purchase order is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 282.
Why This Is the Correct Answer
Purchase order is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 282.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Vertical reinforcing is required at 32 in. on center along an 80 ft CMU wall, with a bar at each end. Each bar length including splice projection is 15 ft. What total reinforcing length is needed?
Next Question
A storefront opening is 48 ft wide and 10 ft high. Deduct two aluminum entrance doors, each 3 ft by 7 ft, from the glazed area. What net glass area remains?
