On the finish plan, locate room R364; then use the finish schedule. What wall finish is listed?

Correct Answer

B) P-2

Sheet F-816 shows R364 on the plan excerpt; the matching schedule row lists P-2 in the Wall Finish column.

Answer Options
A
FRP-1
B
P-2
C
WOOD PANEL
D
TILE-3

Why This Is the Correct Answer

Sheet F-816 shows R364 on the plan excerpt; the matching schedule row lists P-2 in the Wall Finish column.

Why the Other Options Are Wrong

Option A: FRP-1

FRP-1 is the wall finish entry for R365, not for the mark located on the plan.

Option C: WOOD PANEL

WOOD PANEL is the wall finish entry for R366, not for the mark located on the plan.

Option D: TILE-3

TILE-3 is the wall finish entry for R367, not for the mark located on the plan.

Memory Technique

Plan-to-table hook for finish and 17: tag R364 selects the row; Wall Finish supplies the field.

Reference Hint

Open Sheet F-816; locate R364 in the plan excerpt before reading the schedule row.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.