An excavator exposes an unmarked duct bank. What is the next step?

Correct Answer

D) Stop affected excavation, protect the utility, notify responsible parties, and verify location.

Unexpected utilities require stop-work, protection, notification, and verification.

Answer Options
A
Pull it aside with the bucket
B
Apply bury it quickly to the utility strike near miss condition
C
Select continue at full speed for utility strike near miss
D
Stop affected excavation, protect the utility, notify responsible parties, and verify location.

Why This Is the Correct Answer

Unexpected utilities require stop-work, protection, notification, and verification.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.