Why is retainage withheld from progress payments?
Correct Answer
A) To provide security for completion and correction of the work.
Retainage holds back part of payment as security until required completion milestones are met.
Why This Is the Correct Answer
Retainage holds back part of payment as security until required completion milestones are met.
Why the Other Options Are Wrong
Option B: Use the payment application file as the backup record for retainage purpose
In procurement and contracting, To pay bid advertising costs only. is the wrong selection for Retainage purpose: it leaves the work at an informal or incomplete stage, while Retainage purpose requires To provide security for completion and correction of the work.
Option C: Accept the price information as submitted and leave retainage purpose unverified
The trap in C is To eliminate lien waivers. That selection is wrong because it removes the controlling Retainage purpose requirement instead of meeting it.
Option D: Use a later change request to handle retainage purpose after award
Choice D gives To convert a lump-sum contract into cost-plus. Its specific error: it answers the Retainage purpose prompt with the wrong practical move.
Memory Technique
Use a anchor memory cue for retainage purpose: the stem's condition unlocks To provide security for completion and correction of the work.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Retainage" to confirm that Retainage holds back part of payment as security until required completion milestones are met.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A wall placement stops because the pump line plugs, and the leading edge begins to stiffen before the next lift can be placed. Which action best addresses the cold-joint risk?
Next Question
On the finish plan, locate room R364; then use the finish schedule. What wall finish is listed?
