A wall form has tight reinforcement, and the concrete supplier asks for the maximum nominal aggregate size allowed by ACI proportioning limits. Which set of limits governs?
Correct Answer
A) Not more than one-fifth the narrowest form dimension, one-third the slab depth, or three-fourths the minimum clear spacing between reinforcement
ACI 318-19 26.4.2.1 limits nominal maximum aggregate size to the smallest of one-fifth the narrowest dimension between forms, one-third the slab depth, and three-fourths the minimum clear spacing between reinforcement. Other choices: the one-half limits are too permissive, one inch is not universal, and pumpability does not override the code limit.
Why This Is the Correct Answer
ACI 318-19 26.4.2.1 limits nominal maximum aggregate size to the smallest of one-fifth the narrowest dimension between forms, one-third the slab depth, and three-fourths the minimum clear spacing between reinforcement.
Why the Other Options Are Wrong
Option B: Not more than one-half the narrowest form dimension, one-half the slab depth, or the full clear spacing between bars
In concrete work, Not more than one-half the narrowest form dimension, one-half the slab depth, or the full clear spacing. is the wrong selection for Aggregate size: the option does not produce the required Aggregate size outcome, Not more than one-fifth the narrowest form dimension, one-third the slab depth, or three-fourths the.
Option C: Exactly one inch for all reinforced concrete
The trap in C is Exactly one inch for all reinforced concrete. That selection is wrong because it describes work from another assembly, while the Aggregate size item is asking for Not more than one-fifth the narrowest form dimension, one-third the slab depth, or three-fourths.; Nominal maximum aggregate size is capped by 1/5 form dimension, 1/3 slab depth, and 3/4 clear reinforcement spacing.
Option D: The largest aggregate the pump can move without plugging
Choice D gives The largest aggregate the pump can move without plugging. Its specific error: the action skips the timing, documentation, or field-control step needed for Aggregate size.
Memory Technique
Treat aggregate size like a labeled shelf; only the matching condition belongs with Not more than one-fifth the narrowest form dimension, one-third the slab depth, or three-fourths the minimum clear spacing.
Reference Hint
Open ACI 318-19, Building Code Requirements for Structural Concrete; use ACI 318-19 26.4.2.1 to confirm that ACI 318-19 26.4.2.1 limits nominal maximum aggregate size to the smallest of one-fifth the narrowest dimension between forms, one-third the slab depth, and three-fourths the minimum clear spacing between reinforcement.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass