The bid quantity for unsuitable soil was 500 cy at $38/cy. Field measurements show 620 cy. What added payment is due for the overrun?
Correct Answer
A) $4,560
The overrun is 620 - 500 = 120 cy. Added payment is 120 x $38 = $4,560. Other choices use 100 cy, 110 cy, or the full measured quantity.
Why This Is the Correct Answer
The overrun is 620 - 500 = 120 cy. Added payment is 120 x $38 = $4,560. Other choices use 100 cy, 110 cy, or the full measured quantity.
Why the Other Options Are Wrong
Option B: $3,800
unit price adjustment, choice a: $3,800 prices 100 units at $38.
Option C: $4,180
unit price adjustment, choice b: $4,180 is wrong because $4,180 prices 110 units at $38.
Option D: $23,560
unit price adjustment, choice d: $23,560 prices 620 units at $38, using 620 from the stem instead of the accepted quantity 120. Unit-price check.
Memory Technique
Picture a scope box labeled unit price adjustment: finish every operation before accepting $4,560.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Unit-price quantity adjustment" to confirm that The overrun is 620 - 500 = 120 cy.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
