The bid quantity for unsuitable soil was 500 cy at $38/cy. Field measurements show 620 cy. What added payment is due for the overrun?

Correct Answer

A) $4,560

The overrun is 620 - 500 = 120 cy. Added payment is 120 x $38 = $4,560. Other choices use 100 cy, 110 cy, or the full measured quantity.

Answer Options
A
$4,560
B
$3,800
C
$4,180
D
$23,560

Why This Is the Correct Answer

The overrun is 620 - 500 = 120 cy. Added payment is 120 x $38 = $4,560. Other choices use 100 cy, 110 cy, or the full measured quantity.

Why the Other Options Are Wrong

Option B: $3,800

unit price adjustment, choice a: $3,800 prices 100 units at $38.

Option C: $4,180

unit price adjustment, choice b: $4,180 is wrong because $4,180 prices 110 units at $38.

Option D: $23,560

unit price adjustment, choice d: $23,560 prices 620 units at $38, using 620 from the stem instead of the accepted quantity 120. Unit-price check.

Memory Technique

Picture a scope box labeled unit price adjustment: finish every operation before accepting $4,560.

Reference Hint

Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Unit-price quantity adjustment" to confirm that The overrun is 620 - 500 = 120 cy.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.