NASCLAProcurement and Contracting Requirementsmedium

The bid quantity for unsuitable soil was 500 cy at $38/cy. Field measurements show 620 cy. What added payment is due for the overrun?

Correct Answer

A) $4,560

The overrun is 620 - 500 = 120 cy. Added payment is 120 x $38 = $4,560. Other choices use 100 cy, 110 cy, or the full measured quantity.

Answer Options
A
$4,560
B
$3,800
C
$4,180
D
$23,560

Why This Is the Correct Answer

The overrun is 620 - 500 = 120 cy. Added payment is 120 x $38 = $4,560. Other choices use 100 cy, 110 cy, or the full measured quantity.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.