In an area where ice dams are a code concern, how far must the roof ice barrier extend into the building under the IBC roof-underlayment rule?
Correct Answer
D) At least 24 in. inside the exterior wall line
The IBC ice-barrier rule requires the barrier to extend from the lowest roof edges to a point at least 24 in. inside the exterior wall line of the building. Other choices stop too soon or overextend the requirement into a full-roof membrane.
Why This Is the Correct Answer
The IBC ice-barrier rule requires the barrier to extend from the lowest roof edges to a point at least 24 in. inside the exterior wall line of the building. Other choices stop too soon or overextend the requirement into a full-roof membrane.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
