A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
Correct Answer
B) Include the stated allowance amount and later adjust for the actual approved cost as required
A stated allowance is included in the contract sum and adjusted later according to the actual approved cost or contract terms. Other choices omit required money, inflate it without basis, or use it for the wrong purpose.
Why This Is the Correct Answer
A stated allowance is included in the contract sum and adjusted later according to the actual approved cost or contract terms. Other choices omit required money, inflate it without basis, or use it for the wrong purpose.
Why the Other Options Are Wrong
Option A: The contractor should exclude the entire allowance from the base bid
The trap in A is Exclude the entire allowance from the base bid. That selection is wrong because it names a financial document or payment mechanism, not the Allowances action/result stated by Include the stated allowance amount and later adjust for the actual approved cost as required; A stated allowance is included in the bid or contract sum and later adjusted under the contract terms.
Option C: The contractor should double the allowance to cover contingency
Choice C (Double the allowance to cover contingency) is rejected because the choice would not get the project to Include the stated allowance amount and later adjust for the actual approved cost as required, which is the Allowances result verified by the source.
Option D: The contractor should use the allowance only for contractor overhead
In procurement and contracting, Use the allowance only for contractor overhead is the wrong selection for Allowances: it tries to bypass the Allowances checkpoint.
Memory Technique
Use a label memory cue for allowances: the stem's condition unlocks Include the stated allowance amount and later adjust for the actual approved cost as required.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Allowances in contract documents" to confirm that A stated allowance is included in the contract sum and adjusted later according to the actual approved cost or contract terms.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass