At closeout, the project engineer checks one requirement: a unit-price item overruns by 449 cy at $157/cy. What added payment is due?
Correct Answer
A) $70,493
The calculation gives $70,493 for the stated unit price addition. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 297.
Why This Is the Correct Answer
The calculation gives $70,493 for the stated unit price addition.
Why the Other Options Are Wrong
Option B: $63,443
unit price addition, choice a: $63,443 is wrong because $63,443 prices 404.1 units at $157.
Option C: $77,542
unit price addition, choice c: $77,542 prices 493.9 units at $157.
Option D: $88,116
unit price addition, choice d: $88,116 is wrong because $88,116 prices 561.25 units at $157.
Memory Technique
Picture a ledger line labeled unit price addition: finish every operation before accepting $70,493.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "unit price addition calculation" to confirm that The calculation gives $70,493 for the stated unit price addition.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A superintendent receives a verbal direction to add temporary heat for finished drywall, but the contract requires written authorization for extra work. What should be done before relying on payment?
Next Question
Six reinforced masonry pilaster spaces each have a clear grout area of 8 in. by 8 in. and a height of 10 ft. Ignoring waste, what grout volume is required?
