At closeout, the project engineer checks one requirement: a unit-price item overruns by 449 cy at $157/cy. What added payment is due?

Correct Answer

A) $70,493

The calculation gives $70,493 for the stated unit price addition. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 297.

Answer Options
A
$70,493
B
$63,443
C
$77,542
D
$88,116

Why This Is the Correct Answer

The calculation gives $70,493 for the stated unit price addition.

Why the Other Options Are Wrong

Option B: $63,443

unit price addition, choice a: $63,443 is wrong because $63,443 prices 404.1 units at $157.

Option C: $77,542

unit price addition, choice c: $77,542 prices 493.9 units at $157.

Option D: $88,116

unit price addition, choice d: $88,116 is wrong because $88,116 prices 561.25 units at $157.

Memory Technique

Picture a ledger line labeled unit price addition: finish every operation before accepting $70,493.

Reference Hint

Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "unit price addition calculation" to confirm that The calculation gives $70,493 for the stated unit price addition.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.