EstatePass
NASCLAContractsmedium27% of exam part

A superintendent receives a verbal direction to add temporary heat for finished drywall, but the contract requires written authorization for extra work. What should be done before relying on payment?

Correct Answer

C) Confirm the direction in writing and follow the contract change or notice procedure

When the contract requires written authorization, the contractor should document the direction and follow the change or notice procedure. Other choices create payment risk or remove required protection.

Answer Options
A
Proceed silently and price it at final payment
B
Treat the verbal direction as a bid alternate
C
Confirm the direction in writing and follow the contract change or notice procedure
D
The superintendent should delete temporary heat from the schedule

Why This Is the Correct Answer

When the contract requires written authorization, the contractor should document the direction and follow the change or notice procedure. Other choices create payment risk or remove required protection.

Why the Other Options Are Wrong

Option A: Proceed silently and price it at final payment

Choice A gives Proceed silently and price it at final payment. Its specific error: the option answers a paperwork, payment, or bonding issue.

Option B: Treat the verbal direction as a bid alternate

Choice B (Treat the direction as a bid alternate) is rejected because it shifts the question into contract administration money flow.

Option D: The superintendent should delete temporary heat from the schedule

The trap in D is Delete temporary heat from the schedule. That selection is wrong because the option tries to substitute, waive, or delete the Undocumented direction control; the item instead requires Confirm the direction in writing and follow the contract change or notice procedure; Extra work should be authorized and noticed as required by the contract.

Memory Technique

Pair undocumented direction with the real field trigger, then choose the response that produces Confirm the direction in writing and follow the contract change or notice procedure.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Written authorization for extra work" to confirm that When the contract requires written authorization, the contractor should document the direction and follow the change or notice procedure.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.