A superintendent receives a verbal direction to add temporary heat for finished drywall, but the contract requires written authorization for extra work. What should be done before relying on payment?
Correct Answer
C) Confirm the direction in writing and follow the contract change or notice procedure
When the contract requires written authorization, the contractor should document the direction and follow the change or notice procedure. Other choices create payment risk or remove required protection.
Why This Is the Correct Answer
When the contract requires written authorization, the contractor should document the direction and follow the change or notice procedure. Other choices create payment risk or remove required protection.
Why the Other Options Are Wrong
Option A: Proceed silently and price it at final payment
Choice A gives Proceed silently and price it at final payment. Its specific error: the option answers a paperwork, payment, or bonding issue.
Option B: Treat the verbal direction as a bid alternate
Choice B (Treat the direction as a bid alternate) is rejected because it shifts the question into contract administration money flow.
Option D: The superintendent should delete temporary heat from the schedule
The trap in D is Delete temporary heat from the schedule. That selection is wrong because the option tries to substitute, waive, or delete the Undocumented direction control; the item instead requires Confirm the direction in writing and follow the contract change or notice procedure; Extra work should be authorized and noticed as required by the contract.
Memory Technique
Pair undocumented direction with the real field trigger, then choose the response that produces Confirm the direction in writing and follow the contract change or notice procedure.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Written authorization for extra work" to confirm that When the contract requires written authorization, the contractor should document the direction and follow the change or notice procedure.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
