Field office rental totals $18,900 for 9 months. What is the monthly cost?
Correct Answer
A) $2,100
Monthly cost is $18,900 / 9 = $2,100.
Why This Is the Correct Answer
Monthly cost is $18,900 / 9 = $2,100.
Why the Other Options Are Wrong
Option B: $1,890
temporary facility cost per month, choice a: $1,890 backs into 210 when divided by 9; the accepted setup gives 233.33 on that same base.
Option C: $2,700
temporary facility cost per month, choice c: $2,700 backs into 300 when divided by 9; the accepted setup gives 233.33 on that same base.
Option D: $9,450
temporary facility cost per month, choice d: $9,450 backs into 1,050 when divided by 9; the accepted setup gives 233.33 on that same base.
Memory Technique
Remember temporary facility cost per month as "base, adjustment, final unit"; the last unit should read $2,100.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - site logistics / temporary facilities / public protection to confirm that Monthly cost is $18,900 / 9 = $2,100.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?