The field office receives a written instruction: a subcontractor bills for stored equipment without invoice, insurance, or storage evidence. What should payment review do?
Correct Answer
C) Hold that portion until required backup is provided
Hold that portion until required backup is provided is the contract-appropriate response: the distractors either bypass required review, conceal a defect, or create a payment or quality dispute in scenario item 385.
Why This Is the Correct Answer
Hold that portion until required backup is provided is the contract-appropriate response
Why the Other Options Are Wrong
Option A: Pay automatically; under a different bidding requirement
In procurement and contracting, Pay automatically; under a different bidding requirement is the wrong selection for Stored material: the option answers a paperwork, payment, or bonding issue.
Option B: Convert it to liquidated damages
The trap in B is Convert it to liquidated damages. That selection is wrong because the choice would not get the project.
Option D: Delete retainage
Choice D (Delete retainage) is rejected because the option tries to substitute, waive, or delete the Stored material control; the item instead requires.
Memory Technique
Use the phrase "problem, control, result" for stored material; the result side is Hold that portion until required backup is provided.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Stored material controls" to confirm that Hold that portion until required backup is provided is the contract-appropriate response
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass