A tenant clinic remains open next to demolition work. What project control should be coordinated?

Correct Answer

D) Phasing, noise/dust controls, access separation, and communication with occupants.

Occupied work requires controls that protect operations and occupants while maintaining construction progress.

Answer Options
A
Base the occupied building noise plan response on the bid bond value
B
Base the occupied building noise plan response on the final warranty date
C
Treat the condition as requiring no controls because demolition is temporary
D
Phasing, noise/dust controls, access separation, and communication with occupants.

Why This Is the Correct Answer

Occupied work requires controls that protect operations and occupants while maintaining construction progress.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.