A lighting panel is planned on a wall that will receive gypsum board and tenant storage shelving nearby. What should be verified before the framing inspection is signed off?
Correct Answer
D) That the installed layout leaves clear working depth in front of the panel for operation and maintenance
Before framing and storage layouts are accepted, the contractor should verify that the panel will have clear working depth for safe operation and maintenance. Finish color, later tenant movement, and closeout paperwork do not solve a physical access obstruction in front of electrical equipment.
Why This Is the Correct Answer
Before framing and storage layouts are accepted, the contractor should verify that the panel will have clear working depth for safe operation and maintenance. Finish color, later tenant movement, and closeout paperwork do not solve a physical access obstruction in front of electrical equipment.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
