A concrete washout pit is leaking toward a swale. What should the superintendent do?
Correct Answer
C) Stop use, contain the leak, clean impacted material, and repair or replace the washout.
Concrete washout must be contained and repaired if it leaks.
Why This Is the Correct Answer
Concrete washout must be contained and repaired if it leaks.
Why the Other Options Are Wrong
Option A: Apply flush it with more water to the concrete washout leak condition
The trap in A is Flush it with more water. That selection is wrong because the option does not produce the required Concrete washout leak outcome, Stop use, contain the leak, clean impacted material, and repair or replace the washout.
Option B: Pump it to a storm drain
Choice B gives Pump it to a storm drain. Its specific error: it points to Pump it to a storm drain. but.
Option D: Resolve concrete washout leak after choosing to cover it with topsoil only
In site construction, Cover it with topsoil only. is the wrong selection for Concrete washout leak: it tries to bypass the Concrete washout leak checkpoint.
Memory Technique
Pair concrete washout leak with the real field trigger, then choose the response that produces Stop use, contain the leak, clean impacted material, and repair or replace the washout.
Reference Hint
Open Developing Your Stormwater Pollution Prevention Plan, EPA 833-R-06-004, 2007; use the index entry or section for "EPA 833-R-06-004 - erosion and sediment controls" to confirm that Concrete washout must be contained and repaired if it leaks.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass