A field-glazed storefront lite is resting directly on the metal sill without setting blocks. The installer says sealant will hold it in place. What is the quality concern?
Correct Answer
A) The glass needs proper setting blocks to support weight, maintain edge clearance, and reduce breakage risk
Glass should bear on proper setting blocks so weight is supported, edge clearances are maintained, and point contact breakage is avoided. Other choices misunderstand glass support and drainage.
Why This Is the Correct Answer
Glass should bear on proper setting blocks so weight is supported, edge clearances are maintained, and point contact breakage is avoided. Other choices misunderstand glass support and drainage.
Why the Other Options Are Wrong
Option B: The glass will become fire-rated automatically, leaving field glazing setting blocks unverified
The trap in B is The glass will become fire-rated automatically. That selection is wrong because the option does not produce the required Field glazing setting blocks outcome, The glass needs proper setting blocks to support weight, maintain edge clearance, and reduce breakage.
Option C: Use sealant alone to handle field glazing setting blocks
Choice C gives Sealant alone improves edge bearing. Its specific error: it points to Sealant alone improves edge bearing, but.
Option D: Metal-to-glass contact is required for drainage
Choice D (Metal-to-glass contact is required for drainage) is rejected because it answers the Field glazing setting blocks prompt with the wrong practical move.
Memory Technique
Picture a weep path on the jobsite; field glazing setting blocks is solved by the action that leads to The glass needs proper setting blocks to support weight, maintain edge clearance, and reduce breakage risk.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Field glazing setting blocks and edge clearance" to confirm that Glass should bear on proper setting blocks so weight is supported, edge clearances are maintained, and point contact breakage is avoided.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass