A contractor wants to stop a cast-in-place floor beam pour away from a column line. For beams and slabs, where does ACI direct ordinary floor-system construction joints unless the design permits otherwise?
Correct Answer
B) Within the middle third of the span
ACI 318 provisions for construction joints in floor systems place ordinary joints within the middle third of spans unless the design documents or engineer approve another location. Other choices: the support face, a casual quarter point, or a reinforcing splice location does not match the ACI floor-joint placement rule.
Why This Is the Correct Answer
ACI 318 provisions for construction joints in floor systems place ordinary joints within the middle third of spans unless the design documents or engineer approve another location.
Why the Other Options Are Wrong
Option A: At the face of the support
In concrete work, At the face of the support is the wrong selection for Construction joints: it leaves out the controlling Construction joints result: Within the middle third of the span.
Option C: At any quarter point chosen by the foreman
Choice C gives At any quarter point chosen by the foreman. Its specific error: the option does not produce the required Construction joints outcome, Within the middle third of the span.
Option D: Directly over the largest top bar splice
Choice D (Directly over the largest top bar splice) is rejected because it points to Directly over the largest top bar splice, but.
Memory Technique
File construction joints under a gate: condition first, number or duty second, answer Within the middle third of the span.
Reference Hint
Open ACI 318-19, Building Code Requirements for Structural Concrete; use ACI 318-19 26.5.6 construction joints in floor systems to confirm that ACI 318 provisions for construction joints in floor systems place ordinary joints within the middle third of spans unless the design documents or engineer approve another location.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
