A stair stringer has an overcut beyond the tread-riser intersection at a high-stress corner. The carpenter suggests leaving it because trim will cover the cut. What should the superintendent require?
Correct Answer
B) Replace the stringer or obtain an approved repair before installation
Overcuts at stringer notches can weaken a critical member; the stringer should be replaced or repaired using an approved detail. Other choices conceal or lightly patch a structural cut.
Why This Is the Correct Answer
Overcuts at stringer notches can weaken a critical member; the stringer should be replaced or repaired using an approved detail. Other choices conceal or lightly patch a structural cut.
Why the Other Options Are Wrong
Option A: Cover the overcut with trim and proceed
Choice A gives Cover the overcut with trim and proceed. Its specific error: the option does not produce the required Stair stringer outcome, Replace the stringer or obtain an approved repair before installation.
Option C: Base the stair stringer response on fill the kerf with construction adhesive only
In wood framing, Fill the kerf with construction adhesive only is the wrong selection for Stair stringer: the action skips the timing, documentation, or field-control step needed for Stair stringer.
Option D: Add one finish nail at the overcut, leaving stair stringer unverified
The trap in D is Add one finish nail at the overcut. That selection is wrong because it leaves out the controlling Stair stringer result: Replace the stringer or obtain an approved repair before installation.
Memory Technique
Remember stair stringer by its jobsite consequence: the correct move points to Replace the stringer or obtain an approved repair before installation.
Reference Hint
Open Carpentry and Building Construction, 2016; use the index entry or section for "Stair stringer layout and cutting quality" to confirm that Overcuts at stringer notches can weaken a critical member; the stringer should be replaced or repaired using an approved detail.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A storm pipe run of 432 ft must fall at 1/8 in. per ft. What total fall is required?
Next Question
A contractor wants to stop a cast-in-place floor beam pour away from a column line. For beams and slabs, where does ACI direct ordinary floor-system construction joints unless the design permits otherwise?
