A stair stringer has an overcut beyond the tread-riser intersection at a high-stress corner. The carpenter suggests leaving it because trim will cover the cut. What should the superintendent require?
Correct Answer
B) Replace the stringer or obtain an approved repair before installation
Overcuts at stringer notches can weaken a critical member; the stringer should be replaced or repaired using an approved detail. Other choices conceal or lightly patch a structural cut.
Why This Is the Correct Answer
Overcuts at stringer notches can weaken a critical member; the stringer should be replaced or repaired using an approved detail. Other choices conceal or lightly patch a structural cut.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A storm pipe run of 432 ft must fall at 1/8 in. per ft. What total fall is required?
Next Question
A contractor wants to stop a cast-in-place floor beam pour away from a column line. For beams and slabs, where does ACI direct ordinary floor-system construction joints unless the design permits otherwise?
