What does a performance bond primarily assure?
Correct Answer
A) Completion of the bonded contract obligations if the contractor defaults.
A performance bond assures the owner's contract performance remedy if the contractor defaults.
Why This Is the Correct Answer
A performance bond assures the owner's contract performance remedy if the contractor defaults.
Why the Other Options Are Wrong
Option B: Payment of only the contractor's payroll taxes
In procurement and contracting, Payment of only the contractor's payroll taxes. is the wrong selection for Performance bond purpose: it tries to bypass the Performance bond purpose checkpoint.
Option C: Approval of substitutions
The trap in C is Approval of substitutions. That selection is wrong because the option does not produce the required Performance bond purpose outcome, Completion of the bonded contract obligations if the contractor defaults.
Option D: Treat the performance bond as requiring correction of every design error
Choice D gives Correction of every design error. Its specific error: it points to Correction of every design error. but.
Memory Technique
Make performance bond purpose a tabbed card: cite the exact condition, then choose Completion of the bonded contract obligations if the contractor defaults.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Performance bond" to confirm that A performance bond assures the owner's contract performance remedy if the contractor defaults.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor wants to stop a cast-in-place floor beam pour away from a column line. For beams and slabs, where does ACI direct ordinary floor-system construction joints unless the design permits otherwise?
Next Question
What is the total length of the footing step centerline shown on the drawing?
