What frame material is listed for door D303 in the door schedule?

Correct Answer

D) AL

On Sheet A-613, Mark D303 is the correct row; the Frame cell in that row shows AL.

Answer Options
A
HM
B
WD
C
AL/GL
D
AL

Why This Is the Correct Answer

On Sheet A-613, Mark D303 is the correct row; the Frame cell in that row shows AL.

Why the Other Options Are Wrong

Option A: HM

Choice A is the HM frame shown on several other rows, not D303.

Option B: WD

Choice B is a leaf material on D301, not the frame for D303.

Option C: AL/GL

Choice C is the D303 leaf material, while the question asks for frame material.

Memory Technique

Door Schedule hook: D303 fixes the row, and Frame fixes the cell.

Reference Hint

Open Sheet A-613 in the plan packet, find Mark D303, then move horizontally to the Frame column.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.