A change proposal includes 320 labor-hours at $48/hour plus a 12 percent labor burden. What loaded labor cost should be carried?
Correct Answer
C) $17,203
Base labor is 320 x $48 = $15,360. Applying 12% burden gives $15,360 x 1.12 = $17,203.20, or about $17,203. Other choices omit burden or apply unsupported percentages.
Why This Is the Correct Answer
Base labor is 320 x $48 = $15,360. Applying 12% burden gives $15,360 x 1.12 = $17,203.20, or about $17,203. Other choices omit burden or apply unsupported percentages.
Why the Other Options Are Wrong
Option A: $15,360
loaded labor cost, choice a: the answer choice lifts $15,360 from the working line Base labor is 320 x 48 = 15360.
Option B: $18,432
loaded labor cost, choice c: $18,432 backs into 384 when divided by $48; the accepted setup gives 358.4 on that same base.
Option D: $20,160
loaded labor cost, choice d: $20,160 backs into 63 when divided by 320; the accepted setup gives 53.76 on that same base.
Memory Technique
Keep a release point beside loaded labor cost: if one number is skipped, the option drifts away from $17,203.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Change proposal labor pricing" to confirm that Base labor is 320 x $48 = $15,360.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass