On a fast-track school project, bank excavation is 2835 cy and soil swells 20 percent for hauling. What loose volume is hauled?

Correct Answer

B) 3,402 cy

The calculation gives 3,402 cy for the stated swell volume. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 184.

Answer Options
A
Apply 3402 cy to the swell volume condition
B
3,402 cy
C
Select 3,061 for swell volume
D
Make 3,742 the answer for swell volume

Why This Is the Correct Answer

The calculation gives 3,402 cy for the stated swell volume. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 184.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.