On a fast-track school project, bank excavation is 2835 cy and soil swells 20 percent for hauling. What loose volume is hauled?
Correct Answer
B) 3,402 cy
The calculation gives 3,402 cy for the stated swell volume. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 184.
Why This Is the Correct Answer
The calculation gives 3,402 cy for the stated swell volume.
Why the Other Options Are Wrong
Option A: Apply 3402 cy to the swell volume condition
swell volume, choice a: 3402 cy repeats the numeric result but changes the required label or rounding; 2,835 x 1.2 = 3,402. so the keyed form is 3,402 cy.
Option C: Select 3,061 for swell volume
swell volume, choice b: 3,061 implies about 7.97 percent swell on 2835; the accepted swell calculation is 2,835 x 1.2 = 3,402.
Option D: Make 3,742 the answer for swell volume
swell volume, choice c: 3,742 is wrong because 3,742 implies about 31.99 percent swell on 2835; the accepted swell calculation is 2,835 x 1.2 = 3,402.
Memory Technique
Store swell volume with its last math move; nearby answers are usually unfinished versions of 3,402 cy.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use the index entry or section for "swell volume calculation" to confirm that The calculation gives 3,402 cy for the stated swell volume.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?