A rectangular room is 42 ft by 28 ft. Resilient base is installed around the perimeter, except for two 3 ft door openings. Adding 5 percent waste, what linear footage should be carried?
Correct Answer
C) 140 lf
Room perimeter is 2 x (42 + 28) = 140 lf. Deduct two 3 ft doors: 140 - 6 = 134 lf. Add 5 percent waste: 134 x 1.05 = 140.7 lf, rounded to 141 lf. Because 141 lf is not listed, 140 lf is the closest listed value. Other choices deduct or add the openings incorrectly.
Why This Is the Correct Answer
Room perimeter is 2 x (42 + 28) = 140 lf. Deduct two 3 ft doors: 140 - 6 = 134 lf. Add 5 percent waste: 134 x 1.05 = 140.7 lf, rounded to 141 lf. Because 141 lf is not listed, 140 lf is the closest listed value. Other choices deduct or add the openings incorrectly.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass