A rectangular room is 42 ft by 28 ft. Resilient base is installed around the perimeter, except for two 3 ft door openings. Adding 5 percent waste, what linear footage should be carried?
Correct Answer
C) 140 lf
Room perimeter is 2 x (42 + 28) = 140 lf. Deduct two 3 ft doors: 140 - 6 = 134 lf. Add 5 percent waste: 134 x 1.05 = 140.7 lf, rounded to 141 lf. Because 141 lf is not listed, 140 lf is the closest listed value. Other choices deduct or add the openings incorrectly.
Why This Is the Correct Answer
Room perimeter is 2 x (42 + 28) = 140 lf. Deduct two 3 ft doors: 140 - 6 = 134 lf. Add 5 percent waste: 134 x 1.05 = 140.7 lf, rounded to 141 lf. Because 141 lf is not listed, 140 lf is the closest listed value. Other choices deduct or add the openings incorrectly.
Why the Other Options Are Wrong
Option A: 134 lf
resilient base, choice b: 134 lf is an intermediate from the steps (.
Option B: 147 lf
resilient base, choice c: 147 lf is wrong because 147 lf implies about 9.7% waste on the 134 lf net length; the accepted waste step is 5 percent in.
Option D: 151 lf
resilient base, choice d: 151 lf implies about 12.69% waste on the 134 lf net length; the accepted waste step is 5 percent in.
Memory Technique
Keep a rough-in sticker beside resilient base: if one number is skipped, the option drifts away from 140 lf.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Resilient base takeoff" to confirm that Room perimeter is 2 x (42 + 28) = 140 lf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass