A finish hardware allowance is bought out below the stated allowance amount. What should happen?
Correct Answer
C) Reconcile the underrun according to the contract, often by crediting the owner.
Allowance balances are reconciled according to contract terms.
Why This Is the Correct Answer
Allowance balances are reconciled according to contract terms.
Why the Other Options Are Wrong
Option A: The contractor should keep the entire underrun automatically
In procurement and contracting, Keep the entire underrun automatically. is the wrong selection for Allowance underrun: the choice would not get the project to Reconcile the underrun according to the contract, often by crediting the owner.
Option B: The contractor should hide invoices from the owner
The trap in B is Hide invoices from the owner. That selection is wrong because the action skips the timing, documentation, or field-control step needed for Allowance underrun.
Option D: Convert the allowance to bid security
Choice D (Convert the allowance to bid security.) is rejected because it shifts the question into contract administration money flow.
Memory Technique
Remember allowance underrun by its jobsite consequence: the correct move points to Reconcile the underrun according to the contract, often by crediting the owner.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Allowance underrun" to confirm that Allowance balances are reconciled according to contract terms.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass