A finish hardware allowance is bought out below the stated allowance amount. What should happen?

Correct Answer

C) Reconcile the underrun according to the contract, often by crediting the owner.

Allowance balances are reconciled according to contract terms.

Answer Options
A
The contractor should keep the entire underrun automatically
B
The contractor should hide invoices from the owner
C
Reconcile the underrun according to the contract, often by crediting the owner.
D
Convert the allowance to bid security

Why This Is the Correct Answer

Allowance balances are reconciled according to contract terms.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.