How do responsiveness and responsibility differ in bidding?
Correct Answer
D) Responsiveness concerns the bid's compliance with requirements; responsibility concerns the bidder's capability.
A responsive bid follows bid requirements; a responsible bidder has capacity, integrity, and qualifications.
Why This Is the Correct Answer
A responsive bid follows bid requirements; a responsible bidder has capacity, integrity, and qualifications.
Why the Other Options Are Wrong
Option A: Both mean only lowest price
Choice A (Both mean only lowest price.) is rejected because it leaves the work at an informal or incomplete stage, while Responsive versus responsible requires Responsiveness concerns the bid's compliance with requirements; responsibility concerns the.
Option B: Responsiveness is post-completion warranty service
In procurement and contracting, Responsiveness is post-completion warranty service. is the wrong selection for Responsive versus responsible: it points to Responsiveness is post-completion warranty service. but.
Option C: Responsibility means the owner must accept any bid
The trap in C is Responsibility means the owner must accept any bid. That selection is wrong because it shifts the question into contract administration money flow.
Memory Technique
Use responsive versus responsible as the label and Responsiveness concerns the bid's compliance with requirements; responsibility concerns the bidder's capability. as the definition to recall under pressure.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Bidder evaluation" to confirm that A responsive bid follows bid requirements; a responsible bidder has capacity, integrity, and qualifications.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass