During turnover document review, what should a bidder do when the bid form requests acknowledgment of Addendum 4?
Correct Answer
B) Acknowledge Addendum 4 and include its scope
Acknowledge Addendum 4 and include its scope is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 242.
Why This Is the Correct Answer
Acknowledge Addendum 4 and include its scope is the controlling requirement
Why the Other Options Are Wrong
Option A: The bidder should ignore it if no price changes
Choice A (Ignore it if no price changes) is rejected because it tries to bypass the Addendum acknowledgment checkpoint.
Option C: Carry it as a post-award claim
The trap in C is Carry it as a post-award claim. That selection is wrong because it answers the Addendum acknowledgment prompt with the wrong practical move.
Option D: The bidder should use only the original drawings
Choice D gives Use only the original drawings. Its specific error: the action skips the timing, documentation, or field-control step needed for Addendum acknowledgment.
Memory Technique
File addendum acknowledgment under a label: condition first, number or duty second, answer Acknowledge Addendum 4 and include its scope.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Addenda acknowledgment" to confirm that Acknowledge Addendum 4 and include its scope is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?