A temporary floor-hole cover is installed in a work area. What marking is required?
Correct Answer
A) Marked with 'HOLE' or 'COVER'
OSHA requires covers for holes to be color coded or marked with the word HOLE or COVER to warn of the hazard.
Why This Is the Correct Answer
OSHA requires covers for holes to be color coded or marked with the word HOLE or COVER to warn of the hazard.
Why the Other Options Are Wrong
Option B: Marked only with the subcontractor name
Choice B gives Marked only with the subcontractor name. Its specific error: it leaves the work at an informal or incomplete stage, while Floor hole cover marking requires Marked with 'HOLE' or 'COVER'. The accepted answer is Marked with 'HOLE' or 'COVER'.
Option C: No marking if painted yellow
Choice C (No marking if painted yellow) is rejected because it describes work from another assembly, while the Floor hole cover marking item is asking for Marked with 'HOLE' or 'COVER'. The cited answer is Marked with 'HOLE' or 'COVER'.
Option D: Marked only on the underside
In general project requirements, Marked only on the underside is the wrong selection for Floor hole cover marking: the action skips the timing, documentation, or field-control step needed for Floor hole cover marking.
Memory Technique
Make floor hole cover marking a tabbed card: cite the exact condition, then choose Marked with 'HOLE' or 'COVER'.
Reference Hint
Open 29 CFR Part 1926 (OSHA Construction Standards), 1926-2023 / PSI OSHA Excerpts 2025; use 29 CFR 1926 Subpart M - Β§1926.501(b) to confirm that OSHA requires covers for holes to be color coded or marked with the word HOLE or COVER to warn of the hazard.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?