A 4000 psi normalweight concrete mix is being evaluated from standard strength tests. Which ACI 318 result set satisfies the acceptance rule for compressive strength?
Correct Answer
B) The average of any three consecutive tests is at least 4000 psi, and no test is below 3500 psi.
For specified strength of 5000 psi or less, ACI 318-19 26.12.3.1 accepts concrete when the average of any three consecutive strength tests is at least f'c and no strength test falls more than 500 psi below f'c; for 4000 psi that floor is 3500 psi. Other choices: requiring every cylinder to reach 4000 psi is too strict, a whole-project average is the wrong window, and the 10 percent branch is for strengths above 5000 psi.
Why This Is the Correct Answer
For specified strength of 5000 psi or less, ACI 318-19 26.12.3.1 accepts concrete when the average of any three consecutive strength tests is at least f'c and no strength test falls more than 500 psi below f'c; for 4000 psi that floor is 3500 psi. Other choices: requiring every cylinder to reach 4000 psi is too strict, a whole-project average is the wrong window, and the 10 percent branch is for strengths above 5000 psi.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?