A responsible bidder is best described as a bidder that:
Correct Answer
A) Has the capability, resources, and qualifications to perform the contract
Responsibility concerns the bidder's qualifications, capability, resources, and reliability. Other choices confuse responsibility with price, lateness, or refusal to meet requirements.
Why This Is the Correct Answer
Responsibility concerns the bidder's qualifications, capability, resources, and reliability. Other choices confuse responsibility with price, lateness, or refusal to meet requirements.
Why the Other Options Are Wrong
Option B: Always submits the lowest number regardless of scope
Choice B gives Always submits the lowest number regardless of scope. Its specific error: it leaves out the controlling Responsible bidder result: Has the capability, resources, and qualifications to perform the contract.
Option C: Select arrives after bid opening for responsible bidder
Choice C (Arrives after bid opening) is rejected because it names a financial document or payment mechanism, not the Responsible bidder action/result stated by Has the capability, resources, and qualifications to perform the contract.
Option D: Make refuses to provide bonds the answer for responsible bidder, leaving responsible bidder unverified
In procurement and contracting, Refuses to provide bonds is the wrong selection for Responsible bidder: the option answers a paperwork, payment, or bonding issue.
Memory Technique
Attach responsible bidder to a anchor: remember the function, then the wording Has the capability, resources, and qualifications to perform the contract.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Responsible bidder concept" to confirm that Responsibility concerns the bidder's qualifications, capability, resources, and reliability.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass