Why is a short-interval look-ahead schedule used during construction?
Correct Answer
D) To coordinate near-term constraints, crews, materials, and inspections.
Look-ahead planning turns the master plan into near-term coordination and constraint removal. It does not waive contract controls.
Why This Is the Correct Answer
Look-ahead planning turns the master plan into near-term coordination and constraint removal. It does not waive contract controls.
Why the Other Options Are Wrong
Option A: Use look-ahead planning to replace the master schedule permanently
The trap in A is To replace the master schedule permanently. That selection is wrong because the option tries to substitute, waive, or delete the Look-ahead planning control; the item instead requires To coordinate near-term constraints, crews, materials, and inspections.; Look-ahead schedules coordinate near-term constraints and work readiness.
Option B: Use look-ahead planning to waive permit inspections
Choice B gives To waive permit inspections. Its specific error: it removes the controlling Look-ahead planning requirement instead of meeting it.
Option C: Use look-ahead planning to approve substitutions without review
Choice C (To approve substitutions without review.) is rejected because the action skips the timing, documentation, or field-control step needed for Look-ahead planning.
Memory Technique
Make look-ahead planning a purpose cue; if the choice changes the purpose, it cannot be To coordinate near-term constraints, crews, materials, and inspections.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - duration / float / baseline / updating / variance to confirm that Look-ahead planning turns the master plan into near-term coordination and constraint removal.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A 4000 psi normalweight concrete mix is being evaluated from standard strength tests. Which ACI 318 result set satisfies the acceptance rule for compressive strength?
Next Question
A corridor finish is specified as IBC Class B interior wall finish. Which flame-spread index range corresponds to Class B?
