A 36 in. nominal swinging door is installed in a frame where stops and door thickness reduce clear opening by 3-1/2 in. when open 90 degrees. What clear opening remains?
Correct Answer
C) 32-1/2 in.
Clear opening is 36 - 3.5 = 32.5 in., which is 32-1/2 in. Other choices subtract too much, use a rounded reduction, or ignore part of the stop and door thickness reduction.
Why This Is the Correct Answer
Clear opening is 36 - 3.5 = 32.5 in., which is 32-1/2 in. Other choices subtract too much, use a rounded reduction, or ignore part of the stop and door thickness reduction.
Why the Other Options Are Wrong
Option A: 30-1/2 in.
door leaf clearance, choice a: 90 / 3 gives 30-1/2 in. That calculation follows divides those two listed numbers.
Option B: 31 in.
door leaf clearance, choice b: 31 in. backs into 62 when divided by 1/2; the accepted setup gives 64 on that same base.
Option D: 33 in.
door leaf clearance, choice d: 33 in. is produced by 36 - 3. The error is using that partial/alternate setup instead of Clear opening is 36 - 3.5 = 32.5 in. which is 32-1/2 in.
Memory Technique
Say the door leaf clearance rule aloud as a chain; the chain ends at 32-1/2 in., not an intermediate stop.
Reference Hint
Open ICC A117.1-2017 Accessible and Usable Buildings and Facilities; use the index entry or section for "ICC A117.1-2017 clear opening measurement at doors" to confirm that Clear opening is 36 - 3.5 = 32.5 in., which is 32-1/2 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?