A connector is making a beam connection 34 ft above grade. Under OSHA steel erection, which fall-protection threshold has been exceeded for connector work?
Correct Answer
C) More than two stories or 30 ft, whichever is less
OSHA 1926.760(b)(1) requires connectors to be protected from fall hazards of more than two stories or 30 ft above a lower level, whichever is less. Other choices use unrelated construction thresholds or timing conditions that do not state the connector rule.
Why This Is the Correct Answer
OSHA 1926.760(b)(1) requires connectors to be protected from fall hazards of more than two stories or 30 ft above a lower level, whichever is less. Other choices use unrelated construction thresholds or timing conditions that do not state the connector rule.
Why the Other Options Are Wrong
Option A: Apply the More than 10 ft limit to the connector fall protection check
In metals work, More than 10 ft is the wrong selection for Connector fall protection: More than 10 ft is the wrong OSHA fall-protection number for the item asked.
Option B: Base the connector fall protection response on the 6 ft construction threshold only
The trap in B is Only the 6 ft construction threshold. That selection is wrong because Only the 6 ft construction threshold is the wrong OSHA fall-protection number for the item asked.
Option D: Base the connector fall protection response on after the final bolt is tensioned
Choice D (Only after the final bolt is tensioned) is rejected because the action skips the timing, documentation, or field-control step needed for Connector fall protection.
Memory Technique
File connector fall protection under a stormwater map: condition first, number or duty second, answer More than two stories or 30 ft, whichever is less.
Reference Hint
Open 29 CFR Part 1926, Subpart R - Steel Erection; use 29 CFR 1926.760(b)(1) to confirm that OSHA 1926.760(b)(1) requires connectors to be protected from fall hazards of more than two stories or 30 ft above a lower level, whichever is less.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
