A schedule update shows that the activity delaying turnover sits on the critical path, while another late activity still has ten days of float. Where should recovery planning focus first?
Correct Answer
C) On the critical-path delay affecting project completion
Critical-path delays control the project completion date, so recovery planning should first address the activity delaying completion. Other choices chase noncontrolling or irrelevant work.
Why This Is the Correct Answer
Critical-path delays control the project completion date, so recovery planning should first address the activity delaying completion. Other choices chase noncontrolling or irrelevant work.
Why the Other Options Are Wrong
Option A: Only on the activity with the most remaining float
The trap in A is Only on the activity with the most remaining float. That selection is wrong because it leaves the work at an informal or incomplete stage, while Critical-path recovery requires On the critical-path delay affecting project completion; Recovery should prioritize delays on the critical path because they affect completion.
Option B: On whichever subcontractor complains first
Choice B gives On whichever subcontractor complains first. Its specific error: it points to On whichever subcontractor complains first, but.
Option D: On completed activities because they are easier to update
In general project requirements, On completed activities because they are easier to update is the wrong selection for Critical-path recovery: it leaves out the controlling Critical-path recovery result: On the critical-path delay affecting project completion.
Memory Technique
Remember critical-path recovery by its jobsite consequence: the correct move points to On the critical-path delay affecting project completion.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Critical-path schedule management" to confirm that Critical-path delays control the project completion date, so recovery planning should first address the activity delaying completion.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
