EstatePass
NASCLAGeneral Reqmedium22% of exam part

A schedule update shows that the activity delaying turnover sits on the critical path, while another late activity still has ten days of float. Where should recovery planning focus first?

Correct Answer

C) On the critical-path delay affecting project completion

Critical-path delays control the project completion date, so recovery planning should first address the activity delaying completion. Other choices chase noncontrolling or irrelevant work.

Answer Options
A
Only on the activity with the most remaining float
B
On whichever subcontractor complains first
C
On the critical-path delay affecting project completion
D
On completed activities because they are easier to update

Why This Is the Correct Answer

Critical-path delays control the project completion date, so recovery planning should first address the activity delaying completion. Other choices chase noncontrolling or irrelevant work.

Why the Other Options Are Wrong

Option A: Only on the activity with the most remaining float

The trap in A is Only on the activity with the most remaining float. That selection is wrong because it leaves the work at an informal or incomplete stage, while Critical-path recovery requires On the critical-path delay affecting project completion; Recovery should prioritize delays on the critical path because they affect completion.

Option B: On whichever subcontractor complains first

Choice B gives On whichever subcontractor complains first. Its specific error: it points to On whichever subcontractor complains first, but.

Option D: On completed activities because they are easier to update

In general project requirements, On completed activities because they are easier to update is the wrong selection for Critical-path recovery: it leaves out the controlling Critical-path recovery result: On the critical-path delay affecting project completion.

Memory Technique

Remember critical-path recovery by its jobsite consequence: the correct move points to On the critical-path delay affecting project completion.

Reference Hint

Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Critical-path schedule management" to confirm that Critical-path delays control the project completion date, so recovery planning should first address the activity delaying completion.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.