Parapet coping is needed around a rectangular roof that is 180 ft by 96 ft. Two 12 ft equipment-screen gaps are excluded. What coping length is required before waste?
Correct Answer
B) 528 ft
The full perimeter is 2 x (180 + 96) = 552 ft. Two excluded 12 ft gaps remove 24 ft, leaving 552 - 24 = 528 ft. Other choices ignore the gaps, add them, or subtract too much.
Why This Is the Correct Answer
The full perimeter is 2 x (180 + 96) = 552 ft. Two excluded 12 ft gaps remove 24 ft, leaving 552 - 24 = 528 ft. Other choices ignore the gaps, add them, or subtract too much.
Why the Other Options Are Wrong
Option A: 552 ft
flashing length, choice a: the answer choice lifts 552 ft from the working line.
Option C: 576 ft
flashing length, choice b: 576 ft backs into 1.04 when divided by 552; the accepted setup gives 0.96 on that same base.
Option D: 504 ft
flashing length, choice c: 504 ft backs into 252 when divided by 2; the accepted setup gives 264 on that same base.
Memory Technique
Remember flashing length as "base, adjustment, final unit"; the last unit should read 528 ft.
Reference Hint
Open Roofing Construction and Estimating, Atcheson, 1995/2022 reprint; use the index entry or section for "Parapet coping and flashing length takeoff" to confirm that The full perimeter is 2 x (180 + 96) = 552 ft.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?