On the window plan, locate window W84; then use the window schedule. What frame is listed?
Correct Answer
C) WOOD
Sheet A-803 shows W84 on the plan excerpt; the matching schedule row lists WOOD in the Frame column.
Why This Is the Correct Answer
Sheet A-803 shows W84 on the plan excerpt; the matching schedule row lists WOOD in the Frame column.
Why the Other Options Are Wrong
Option A: FRP
FRP is the frame entry for W81, not for the mark located on the plan.
Option B: AL
AL is the frame entry for W82, not for the mark located on the plan.
Option D: HM
HM is the frame entry for W83, not for the mark located on the plan.
Memory Technique
In window and 04, W84 bridges plan to schedule; Frame is the only cell to answer from.
Reference Hint
Open Sheet A-803; locate W84 in the plan excerpt before reading the schedule row.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass