From the sediment berm plan, what is the total centerline length of the four shown segments?
Correct Answer
B) 102 ft
The segmented berm length is the sum of all four labeled portions.
Why This Is the Correct Answer
The segmented berm length is the sum of all four labeled portions.
Why the Other Options Are Wrong
Option A: 74 ft
Choice A omits the 28 ft final berm segment.
Option C: 50 ft
Choice C adds only the 32 ft and 18 ft middle segments.
Option D: 120 ft
Choice D adds an extra 18 ft segment that is not shown.
Memory Technique
For sediment berm segment, chain labels add; scale guessing stays out.
Reference Hint
Open Sheet C-239; locate the named site feature and use the shown dimensions or scale bar exactly as described.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?