Using the slab panel dimensions and 9 in. thickness, what concrete volume is shown?
Correct Answer
D) 16.9 cy
The slab panel volume is length times width times 9 in. thickness, divided by 27 cubic feet per cubic yard.
Why This Is the Correct Answer
The slab panel volume is length times width times 9 in. thickness, divided by 27 cubic feet per cubic yard.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A T&M material ticket includes $9,600 of approved materials. The contract allows 8 percent sales tax and 10 percent markup after tax. What material amount should be billed?
Next Question
Excavated soil is being placed along a trench edge while pipe bedding is installed below. What minimum setback or equivalent protection does OSHA require for spoil piles?