Excavated soil is being placed along a trench edge while pipe bedding is installed below. What minimum setback or equivalent protection does OSHA require for spoil piles?
Correct Answer
D) Spoils must be kept at least 2 ft from the excavation edge or restrained from falling in
OSHA 1926.651(j)(2) requires employees to be protected from excavated or other materials by placing and keeping them at least 2 ft from the edge of excavations, or by retaining devices sufficient to prevent materials from falling or rolling into excavations. Other choices put surcharge and falling material too close to the trench.
Why This Is the Correct Answer
OSHA 1926.651(j)(2) requires employees to be protected from excavated or other materials by placing and keeping them at least 2 ft from the edge of excavations, or by retaining devices sufficient to prevent materials from falling or rolling into excavations. Other choices put surcharge and falling material too close to the trench.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?