EstatePass
NASCLAContractsmedium27% of exam part

A project has long-lead curtain wall anchors and switchboards. What should a procurement log track for those items?

Correct Answer

D) Submittal, approval, release, fabrication, shipping, and required-on-site dates

A procurement log tracks the dates and status needed to get long-lead materials approved, released, fabricated, shipped, and delivered before installation. Other choices omit the procurement controls that protect the schedule.

Answer Options
A
The contractor should track only the final installation date after the long-lead item reaches the site
B
The contractor should track only the supplier contact address and sales representative
C
The contractor should track only weather-delay notes that are not tied to submittal or release dates
D
Submittal, approval, release, fabrication, shipping, and required-on-site dates

Why This Is the Correct Answer

A procurement log tracks the dates and status needed to get long-lead materials approved, released, fabricated, shipped, and delivered before installation. Other choices omit the procurement controls that protect the schedule.

Why the Other Options Are Wrong

Option A: The contractor should track only the final installation date after the long-lead item reaches the site

The trap in A is Only the final punch-list date. That selection is wrong because it leaves the work at an informal or incomplete stage, while Procurement log requires Submittal, approval, release, fabrication, shipping, and required-on-site dates; A procurement log tracks approval, release, fabrication, shipping, and required-on-site dates for long-lead items.

Option B: The contractor should track only the supplier contact address and sales representative

Choice B gives Only the owner's mailing address. Its specific error: the option delays or omits the controlling step.

Option C: The contractor should track only weather-delay notes that are not tied to submittal or release dates

Choice C (Only weather delays) is rejected because the action skips the timing, documentation, or field-control step needed for Procurement log.

Memory Technique

Make procurement log a tabbed card: cite the exact condition, then choose Submittal, approval, release, fabrication, shipping, and required-on-site dates.

Reference Hint

Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Procurement-log management" to confirm that A procurement log tracks the dates and status needed to get long-lead materials approved, released, fabricated, shipped, and delivered before installation.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.