A project has long-lead curtain wall anchors and switchboards. What should a procurement log track for those items?
Correct Answer
D) Submittal, approval, release, fabrication, shipping, and required-on-site dates
A procurement log tracks the dates and status needed to get long-lead materials approved, released, fabricated, shipped, and delivered before installation. Other choices omit the procurement controls that protect the schedule.
Why This Is the Correct Answer
A procurement log tracks the dates and status needed to get long-lead materials approved, released, fabricated, shipped, and delivered before installation. Other choices omit the procurement controls that protect the schedule.
Why the Other Options Are Wrong
Option A: The contractor should track only the final installation date after the long-lead item reaches the site
The trap in A is Only the final punch-list date. That selection is wrong because it leaves the work at an informal or incomplete stage, while Procurement log requires Submittal, approval, release, fabrication, shipping, and required-on-site dates; A procurement log tracks approval, release, fabrication, shipping, and required-on-site dates for long-lead items.
Option B: The contractor should track only the supplier contact address and sales representative
Choice B gives Only the owner's mailing address. Its specific error: the option delays or omits the controlling step.
Option C: The contractor should track only weather-delay notes that are not tied to submittal or release dates
Choice C (Only weather delays) is rejected because the action skips the timing, documentation, or field-control step needed for Procurement log.
Memory Technique
Make procurement log a tabbed card: cite the exact condition, then choose Submittal, approval, release, fabrication, shipping, and required-on-site dates.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Procurement-log management" to confirm that A procurement log tracks the dates and status needed to get long-lead materials approved, released, fabricated, shipped, and delivered before installation.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
