A punched window is set before the sill flashing membrane is lapped into the rough opening. The WRB is already cut around the opening. What should the crew do?
Correct Answer
B) Remove or reset as needed so sill flashing, jamb flashing, head flashing, and WRB laps shed water outward
Window flashing must be installed in water-shedding sequence with the WRB so water drains outward, especially at the sill. Other choices rely on sealant or omit critical parts of the flashing sequence.
Why This Is the Correct Answer
Window flashing must be installed in water-shedding sequence with the WRB so water drains outward, especially at the sill. Other choices rely on sealant or omit critical parts of the flashing sequence.
Why the Other Options Are Wrong
Option A: Proceed and depend on exterior sealant
Choice A (Proceed and depend on exterior sealant) is rejected because it leaves out the controlling Window flashing sequence result: Remove or reset as needed so sill flashing, jamb flashing, head flashing, and WRB laps shed water outward.
Option C: Foam the rough opening and skip flashing
The trap in C is Foam the rough opening and skip flashing. That selection is wrong because the option delays or omits the controlling step.
Option D: Install head flashing only because water runs down and use that item to close window flashing sequence
Choice D gives Install head flashing only because water runs down. Its specific error: the action skips the timing, documentation, or field-control step needed for Window flashing sequence.
Memory Technique
Tag the scene with window flashing sequence: wrong actor or wrong timing means the fix is not Remove or reset as needed so sill flashing, jamb flashing, head flashing, and WRB laps shed water outward.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Window rough-opening flashing sequence" to confirm that Window flashing must be installed in water-shedding sequence with the WRB so water drains outward, especially at the sill.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
