A veneer shelf angle run needs 96 ft of flashing. The crew expects eight field splices, each with a 6 in. lap. What total flashing length should be supplied?
Correct Answer
C) 100 ft
Eight laps at 6 in. each add 48 in., or 4 ft. Total flashing length is 96 + 4 = 100 ft. Other choices: 98 ft uses only four laps, 104 ft assumes 12 in. laps, and 108 ft doubles the lap allowance.
Why This Is the Correct Answer
Eight laps at 6 in. each add 48 in., or 4 ft. Total flashing length is 96 + 4 = 100 ft.
Why the Other Options Are Wrong
Option A: 98 ft
flashing quantity, choice a: 98 ft omits a required add-on/subtraction; the numeric gap is 2.
Option B: 104 ft
flashing quantity, choice c: 104 ft is off by 4 from the checked result 100 ft because it misuses the 4 item (at 6 in).
Option D: 108 ft
flashing quantity, choice d: 108 ft adds an extra unstated add-on/subtraction; the numeric gap is 8.
Memory Technique
Remember flashing quantity as "base, adjustment, final unit"; the last unit should read 100 ft.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Masonry flashing takeoff" to confirm that Eight laps at 6 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?