A contract unit price for pressure grouting is $82/lf. Approved added work measures 145 lf. What added payment is due?
Correct Answer
B) $11,890
Added payment is 145 lf x $82/lf = $11,890. Other choices use 100 lf, 133 lf, or $100/lf rather than the stated unit price.
Why This Is the Correct Answer
Added payment is 145 lf x $82/lf = $11,890. Other choices use 100 lf, 133 lf, or $100/lf rather than the stated unit price.
Why the Other Options Are Wrong
Option A: $8,200
unit-price addition, choice a: $8,200 is wrong because $8,200 prices 100 units at $82.
Option C: $10,890
unit-price addition, choice b: $10,890 prices 132.8 units at $82.
Option D: $14,500
unit-price addition, choice d: $14,500 is wrong because $14,500 prices 176.83 units at $82.
Memory Technique
Remember unit-price addition as "base, adjustment, final unit"; the last unit should read $11,890.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Unit-price added work" to confirm that Added payment is 145 lf x $82/lf = $11,890.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?