An activity had 9 days of total float and a delay consumes 4 days. How much float remains?

Correct Answer

D) 5 days

Remaining float is 9 - 4 = 5 days.

Answer Options
A
4 days
B
9 days
C
13 days
D
5 days

Why This Is the Correct Answer

Remaining float is 9 - 4 = 5 days.

Why the Other Options Are Wrong

Option A: 4 days

float consumption, choice a: 4 days uses the wrong side of the schedule subtraction or omits one duration component.

Option B: 9 days

float consumption, choice c: 9 days is wrong because 9 days uses the wrong side of the schedule subtraction or omits one duration component.

Option C: 13 days

float consumption, choice d: 13 days uses the wrong side of the schedule subtraction or omits one duration component.

Memory Technique

Remember float consumption as "base, adjustment, final unit"; the last unit should read 5 days.

Reference Hint

Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - duration / float / baseline / updating / variance to confirm that Remaining float is 9 - 4 = 5 days.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.