A 44 ft by 28 ft slab will be placed 5 in. thick. Including 6 percent waste, how many cubic yards should be ordered to the nearest tenth?
Correct Answer
A) 20.2 cy
Volume is 44 x 28 x 5/12 = 513.3 cf; 513.3/27 = 19.0 cy; 19.0 x 1.06 = 20.2 cy. Other choices: 19.0 cy omits waste, 21.3 cy uses an excessive waste allowance, and 16.9 cy comes from treating 5 in. as 0.4 ft.
Why This Is the Correct Answer
Volume is 44 x 28 x 5/12 = 513.3 cf; 513.3/27 = 19.0 cy; 19.0 x 1.06 = 20.2 cy.
Why the Other Options Are Wrong
Option B: 19.0 cy
concrete volume, choice b: the answer choice lifts 19.0 cy from the working line 513.3/27 = 19.0 cy.
Option C: 21.3 cy
concrete volume, choice c: 21.3 cy equals about 575.1 cf after cubic-yard conversion; the accepted cubic-foot volume is 513.3 cf before dividing by 27 in.
Option D: 16.9 cy
concrete volume, choice d: 16.9 cy is wrong because 16.9 cy equals about 456.3 cf after cubic-yard conversion; the accepted cubic-foot volume is 513.3 cf before dividing by 27 in.
Memory Technique
Keep a redline beside concrete volume: if one number is skipped, the option drifts away from 20.2 cy.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Concrete quantity takeoff - slab volume" to confirm that Volume is 44 x 28 x 5/12 = 513.3 cf; 513.3/27 = 19.0 cy; 19.0 x 1.06 = 20.2 cy.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass