An anchored brick veneer wall uses adjustable metal anchors. Under the IBC/TMS prescriptive spacing rule, each veneer anchor may support no more than what wall area?
Correct Answer
C) 2.67 sq ft
IBC-referenced anchored masonry veneer provisions limit each veneer anchor to supporting not more than 2.67 sq ft of wall area. Other choices: 1.00 and 2.00 sq ft are more conservative than the prescriptive maximum, while 4.00 sq ft exceeds it.
Why This Is the Correct Answer
IBC-referenced anchored masonry veneer provisions limit each veneer anchor to supporting not more than 2.67 sq ft of wall area.
Why the Other Options Are Wrong
Option A: 1.00 sq ft
In masonry work, 1.00 sq ft is the wrong selection for Anchored veneer ties: 1.00 sq ft is an IBC dimensional value for a different stair, door, or egress condition.
Option B: 2.00 sq ft
The trap in B is 2.00 sq ft. That selection is wrong because 2.00 sq ft is an IBC dimensional value for a different stair, door, or egress condition.
Option D: 4.00 sq ft
Choice D (4.00 sq ft) is rejected because 4.00 sq ft is an IBC dimensional value for a different stair, door, or egress condition.
Memory Technique
Treat anchored veneer ties like a labeled shelf; only the matching condition belongs with 2.67 sq ft.
Reference Hint
Open International Building Code 2021 or 2024; use IBC anchored masonry veneer provisions; TMS 402 prescriptive anchorage to confirm that IBC-referenced anchored masonry veneer provisions limit each veneer anchor to supporting not more than 2.67 sq ft of wall area.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
