An employee is admitted as an inpatient after a trench incident. What OSHA reporting deadline applies?
Correct Answer
A) Within 24 hours
OSHA requires inpatient hospitalization, amputation, or loss of an eye to be reported within 24 hours. Fatalities use the 8-hour deadline.
Why This Is the Correct Answer
OSHA requires inpatient hospitalization, amputation, or loss of an eye to be reported within 24 hours. Fatalities use the 8-hour deadline.
Why the Other Options Are Wrong
Option B: Within 8 hours
The trap in B is Within 8 hours. That selection is wrong because Within 8 hours is a different published number than the cited OSHA hospitalization reporting value; OSHA severe injury reporting supports Within 24 hours; Inpatient hospitalization must be reported to OSHA within 24 hours.
Option C: Only with the annual summary
Choice C gives Only with the annual summary. Its specific error: it tries to bypass the OSHA hospitalization reporting checkpoint.
Option D: At final project closeout
Choice D (At final project closeout) is rejected because the option does not produce the required OSHA hospitalization reporting outcome, Within 24 hours.
Memory Technique
File OSHA hospitalization reporting under a stormwater map: condition first, number or duty second, answer Within 24 hours.
Reference Hint
Open 29 CFR Part 1926 (OSHA Construction Standards), 1926-2023 / PSI OSHA Excerpts 2025; use OSHA reporting / recordkeeping topic to confirm that OSHA requires inpatient hospitalization, amputation, or loss of an eye to be reported within 24 hours.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
An anchored brick veneer wall uses adjustable metal anchors. Under the IBC/TMS prescriptive spacing rule, each veneer anchor may support no more than what wall area?
Next Question
A pump schedule lists a motor in horsepower, but the electrical coordination table uses watts. Which conversion should be recognized for one horsepower?