A long-lead item is needed on site by project day 90. Submittal review takes 14 days, fabrication takes 35 days, and shipping takes 7 days. What is the latest release day to preserve the need date?
Correct Answer
D) Day 34
The required procurement duration is 14 + 35 + 7 = 56 days. The latest release is day 90 - 56 = day 34. Other choices omit one step or subtract the wrong duration.
Why This Is the Correct Answer
The required procurement duration is 14 + 35 + 7 = 56 days. The latest release is day 90 - 56 = day 34. Other choices omit one step or subtract the wrong duration.
Why the Other Options Are Wrong
Option A: Day 28
procurement release date, choice a: 35 - 7 gives Day 28. That calculation subtracts those two listed numbers in that order.
Option B: Day 42
procurement release date, choice b: the number Day 42 comes from 35 + 7.
Option C: Day 56
procurement release date, choice d: Day 56 is an intermediate from the steps (.
Memory Technique
Say the procurement release date rule aloud as a chain; the chain ends at Day 34, not an intermediate stop.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Procurement scheduling" to confirm that The required procurement duration is 14 + 35 + 7 = 56 days.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
