A long-lead item is needed on site by project day 90. Submittal review takes 14 days, fabrication takes 35 days, and shipping takes 7 days. What is the latest release day to preserve the need date?

Correct Answer

D) Day 34

The required procurement duration is 14 + 35 + 7 = 56 days. The latest release is day 90 - 56 = day 34. Other choices omit one step or subtract the wrong duration.

Answer Options
A
Day 28
B
Day 42
C
Day 56
D
Day 34

Why This Is the Correct Answer

The required procurement duration is 14 + 35 + 7 = 56 days. The latest release is day 90 - 56 = day 34. Other choices omit one step or subtract the wrong duration.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.